Tasks Overview Staff Overview Accounting Calendar
Tasks Details Staff Details Status Report GANTT Chart (Postscript)

Accounting Software Project - March 2002

This table shows the load of each day for all the tasks. Additionally the resources used for each task are listed. Since the project start was delayed, the delayed schedule differs significantly from the original plan.

No. Name Start End Scenario Mar 2002
 1  2  3  4  5  6  7  8  9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1. Accounting Software 2002-01-16 2002-04-16 Plan 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 1.8 1.8 == ==
2002-01-20 2002-04-24 Delayed 4 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == ==
2. Milestones 2002-01-16 2002-04-16 Plan == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == ==
2002-01-20 2002-04-24 Delayed == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == ==
3. Technology Preview 2002-03-01 2002-03-01 Plan <>                    
2002-03-06 2002-03-06 Delayed         <>                
4. Manual 2002-01-16 2002-02-26 Plan                      
2002-01-21 2002-03-01 Delayed 2=]                    
  Developers     Plan                      
Delayed 1                    
  Klaus Müller     Plan                      
Delayed 1                    
  The Others     Plan                      
Delayed 1                    
  Dim Sung     Plan                  
Delayed 1                
5. Software Development 2002-01-28 2002-03-27 Plan 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 1=v    
2002-01-31 2002-04-03 Delayed 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == ==
6. Back-End Functions 2002-02-11 2002-03-01 Plan 2=]                    
2002-02-14 2002-03-06 Delayed 2 == == 2 2 2=]                
  Developers     Plan 2                    
Delayed 2   2 2 2                
  Paul Smith     Plan 1                    
Delayed 1   1 1 1                
  Sébastien Bono     Plan 1                    
Delayed 1   1 1 1                
7. Graphical User Interface 2002-03-04 2002-03-27 Plan     [=2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 1=]    
2002-03-07 2002-04-03 Delayed         [=2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == ==
  Developers     Plan     2 2 2 2 2   2 2 2 2 2   2 2 2 2 2   2 2 1    
Delayed         2 2   2 2 2 2 2   2 2 2 2 2   2 2 2 2 2  
  Sébastien Bono     Plan     1 1 1 1 1   1 1 1 1 1   1 1 1 1 1   1 1 0.5    
Delayed         1 1   1 1 1 1 1   1 1 1 1 1   1 1 1 1 1  
  Klaus Müller     Plan     1 1 1 1 1   1 1 1 1 1   1 1 1 1 1   1 1 0.5    
Delayed         1 1   1 1 1 1 1   1 1 1 1 1   1 1 1 1 1  
8. Software testing 2002-03-27 2002-04-16 Plan                     v=1 1.8 1.8 == ==
2002-04-04 2002-04-24 Delayed                      
9. Alpha Test 2002-03-27 2002-04-01 Plan                     [=1 1.8 1.8 == ==
2002-04-04 2002-04-08 Delayed                      
  Developers     Plan                     0.5 1 1  
Delayed                      
  Sébastien Bono     Plan                     0.5 1 1  
Delayed                      
  The Others     Plan                     0.5 0.8 0.8  
Delayed                      
  Peter Murphy     Plan                     0.5 0.8 0.8  
Delayed                      

Version 1.0 - Created on 2005-10-12 with TaskJuggler v2.0.1